12.10.09

Today two month and one day have passed since we started building. During the first month we were almost three people, Him the boatbuilder I know for 17 years now (he built a boat for me then), one worker and me. Now for two weeks there are two painters here who work on the outside, fairing, applying filler and fiberglass and so on.
I made some pictures to show the state now:

First picture: Left side to windward. Seen from the toilet and shower room toward the sleeping cabin (bunk already with primer). Right lower corner a bit of the backrest of the seat, a locker (50 cm), navigation table (80 cm), locker with fridge (the closed square), locker with cooker (80 cm). Left side working on the bulkheads where the cockpit will be glued to, locker (50 cm), locker with sink (80 cm). Behind the doublebunk with locker under (vacuum cleaner inside). Lockers behind the bulkheads not visible.
Pitschi, the cat was here in the house I rent, left from the previous owner. She is very charming and lovely and talks a lot. We love each other so I will keep her.

Second picture: Seen from the other side. In the foreground the lockers in the cabin. The raised floor in front of the shower and toilet is necessary to get enough space between the seats. A folding table will be there.

Third picture: One side of the hull is glassed (one layer mat, one cloth) and smothed with filler (glass bubbles). It will be sanded and faired with filler one or two more times.

 

12.10.10

Some details:
On the first picture you see the toilet and shower room from above. The round beam is the end of the deckhouse.In one of the rounded lockers a sink will be placed. The hole between (about 50 x 60 cm)will be covered with grating and take the shower water that will be pumped out with a small bilge pump. What you see down there is the hull side with the inner keel. Left side of it is the floor with foam under where the toilet will stand on. Left under corner is the storage room behind a bulkhead. Upper right corner is the raised floor between the seats.

In the center of the second picture is the bulkhead on which the cockpit will be fixed on. Two sheets of plywood, 5cm x 5cm frame between. To the left the ladder will be glued on, an opening cut out down to the upper of the two stringer as soon as both bulkheads are finished. To the right side of that bulkhead a locker (50 cm) and the locker with the sink.

Third picture: left side a triangular locker to get enough room to change cloth and move. The bunk and sides are primered, also the bookshelf. A varnished batten will be glued to it. Storage space under the bunks.

We filled nearly all space under the waterline (that is about the floorboards) with foam exept from the water tanks and the waterdrain in the shower room, a space where the batteries will be (under the raised floor between the seats) and a part under the bunk (about 50 cm each of the three). The space beside the rudder trunks and the bow section we filled to about 70 cm above the waterline. I can cut open a lot on a reef and she will still not sink.

I weighed her with a lever arm and actually without deck I came to 870 kg. This method is not precisely but the mainhull is at about or under 900 kg. That is about what I calculated.

 

12.10.14

Some more pictures for a lazy sunday afternoon:
The fridge is isolated with foam.As I could not find closed cell foam I made a 5 cm frame, laied it on the floor, poured 2 component foam into and covered it with a plastic and plywood. so I got my own foam I could cut. The next step will be to cover it inside with glass.
As you can see, the lockers are slightly bent to follow the edge between floor and hull. So I have a floor about 80 cm wide in the center of the boat and about 60 cm in the cabin.

12.10.15

As the doubled bulkheads are glued and screwed now I could cut the opening to the cockpit. I wanted to wait for the bulkheads because I thought the hull could bend slightly in that region when I cut it before. Now it is easier to climb aboard.

12.10.20

Saturday, end of the week. The “fore-” and “after-” deck are covered with plywood. The fridge is foamed and covered with glass and epoxy. All boards and lockers are made, the last ones awaiting painting. All deckbeams are in and we work on the stringers on the cabin roof. Meanwhile the painters sand the hull, put filler on, sand the hull, put filler on ......
On monday my wife will come for holidays. So we will leave for some relaxed days and I will post the next pictures when we will back. Have a nice time

12.11.10

After my holidays we worked the past week mainly on the deckhouse and the wood trim inside. We are actually only Him and me, the painters had to go for different reasons. Even when there are many people unemployed here, it is not easy to find good reliable staff.
There is not a lot more to say now, so look at the pictures.

12.11.18

In the past week, apart from some minor jobs, we decked the deckhouse. It is done with six panels of 6mm plywood, three on each side. Two of the beams are 1.20m from the center, so we could use nearly the whole length of a panel. We screwed it to the center deck stringer first and worked out to the corners then. That way the plywood bended surprisingly well. All the joints exept along the center deck stringer are scarfed 6cm wide. We unscrewed it then, coated it with epoxy and screwed it on again. The four pieces to the rounded end of the deckhouse are smaller, so easier to fit on. Over the edges we glued fibre glass tape with epoxy and covered the whole deck with glass mat and fibreglass cloth then, all in the same afternoon. Now it needs some filler and sanding. The sides of the deckhouse and the fore and after deck we will glass tomorrow. Then the whole outside can be made ready for painting.
The cutouts you see are for the hatches over the shower/toilet room, the table and the sleeping cabin. The small ones beside the rudder trunk are for mooring ropes and fenders.

12.11.24

Actually we are only two people working on Nixe. It is not easy to find people here and things change quickly. We glassed the deck, one man was sanding it and applied filler on it. I was working inside, rounding the edges of the lockers and making the cabin doors. The locker doors are being made now. In the next few days I will have to run around to buy parts for the water system, lamps, wiring and switchboards and all other small bits needed inside